What did we do?
Strict specifications, evolving designs, and fire safety requirements – all delivered under pressure.
Tomlinson Hall was commissioned by a leading design house working within the mining industry to deliver two complete water boosting packages for a major development in Teesside.
The client required a highly bespoke design – both systems had to meet exact technical specifications, including side-wall positioned inlet and outlet connections, and installation within a 30-minute fire retardant enclosure. The project also demanded strict adherence to industry legislation and a fully documented approval process at every stage, including detailed drawings and specification sign-offs.
Frequent design amendments during development added further complexity, requiring a high degree of flexibility, technical accuracy, and collaboration.
Precision-engineered booster sets, designed to perform and built to last.
Working in close partnership with one of our key manufacturing suppliers, we engineered and delivered two bespoke packaged booster systems tailored to the customer’s specific operational and environmental requirements.
-
System 1: A four-pump MARB SP4V unit for processed water
-
System 2: A two-pump MARB SP2V unit for non-saline water transfer
Both units featured full 316-grade stainless steel pipework, bases, manifolds, and fittings, ensuring long-term durability in harsh industrial environments. The enclosures were manufactured to meet the 30-minute fire retardancy standard and colour-matched to the client’s specifications.
The advanced MARB control philosophy provided flexible operating modes, allowing the booster sets to run via pressure control or level control depending on the system configuration.
Full collaboration and documentation throughout a 10-month development timeline.
From initial enquiry through to delivery, our team maintained constant dialogue with the client to address specification changes, coordinate updated drawings, and ensure full regulatory compliance at every stage.
All engineering design, equipment supply, and documentation were delivered ahead of the scheduled deadline, despite the project taking place over an extended 10-month period.
Custom-engineered systems delivered to spec, with full compliance and early completion.
-
Fully bespoke booster sets built exactly to the client’s design and technical specification
-
Fire-retardant enclosures manufactured to a 30-minute safety standard and colour-matched
-
Dual control functionality offering pressure or level-based operation via MARB control
-
Robust stainless steel construction using 316-grade materials for durability
-
Delivered ahead of schedule despite evolving requirements and extended project duration
Why Tomlinson Hall?
Tomlinson Hall delivers bespoke pump and booster systems for industrial, commercial, and residential clients. Whether working to an exact specification or solving a unique challenge, our experienced team provides reliable, future-ready solutions backed by over 100 years of engineering heritage.